Electric stage hoist is a kind of common use tools, many customers operate improperly in the process of using causing many problems, the solution is as follows:
1.Power line phase error, resulting in phase protection to start, so can not be operated.
Solution: change the power line two phase to each other.
2.The power of the fuse or no fuse switch off.
Solution: check the current demand is met or not, the replacement for the fuse or restart no fuse switch.
3.Fuse of control circuit burn out.
Solution: check and replace the fuse.
4.The power line or the cable of the control circuit breakage or not good.
Solution: to repair or replace the broken and poor contact cables.
5.Power supply voltage is too low.
Solution: measure the voltage value is 10% lower than the standard supply voltage or not.
6.The motor makes a sound, but it doesn’t rotate.
Solution: check whether the motor phase is correct or not. Repair and do a good job in insulation.
7.Emergency switch is pressed.
Solution: to confirm the reasons for the emergency switch.
8.Poor contactor.
Solution: manual hoist operations. If the stage hoist act normally, it means the control coil or wire contact poorly, then find out contact bad position and repair; if manually operated electric stage chain hoist is still unable to operate, you need to check mains is fine or not, if there is no title of main power supply,it means the contactor is poor and unable to output the normally, need to replace the contactor.

评论

此博客中的热门博文

How to deal with 3 ton electric chain hoist motor overheating

Any machine has the cycle and time of operation, is not suitable for a long time continuous operation. Long time operation will cause mechanical damage and even accidents, but in general if the 3 ton electric chain hoist surface temperature is too high, we need to check what is the reason. Firstly to check whether it is because the electric hoist weight is too large, beyond the 3 ton electric chain hoist rated weight. Overweight operation will make the motor over heating, overload for a long time will cause irreparable damage to the electric chain hoists for sale.  Electric hoist motor  is not overloaded, but still heating, should check whether the motor bearing damaged; Should also check whether the motor Work according to regulations, which is one of the reasons causing the motor heating. When the electric hoist motor is running, brake clearance is too small, not completely disengaged, causing great friction, while the frictional heating is also equivalent to the additi...

The reason of electrical wire rope hoist does not work after starting

Mainly because of the hoist does not reach to the rated operating voltage, there are generally 3 kinds of situations: 1.Find out whether the power supply system supply power to wire rope electric hoist , generally used test pencil, such as no power supply; 2.The main control circuit of the wire rope electric hoist is damaged, the line is broken or the contact is bad, can also let the hoist motor not be electrified. This situation, need to overhaul the main control circuit. When maintenance, in order to prevent missing phase to burn the motor casused by the main control circuit supply power to three-phase motor, or hoist motor suddenly operate and cause danger, must disconnect electrical wire rope hoist motor from the power supply, only supply power to the main control circuit. Then start and stop switch, check and analyze the working condition of the electric appliance and the line, repair or replace the failed electric appliance or line. When the main control circuit is confirmed...

Overhead gantry crane lifting instructions

The overhead crane in workshop should not use mechanical lifting, because the top of the rail is close to the bottom chord of roof truss, in addition, the volume and weight of the heavy duty gantry crane are large. Small and medium sized overhead travelling gantry crane used single mast upright integral hoisting, which can improve work efficiency, shorten the construction period, reduce high-altitude operations, the construction procedures are as follows. Erecting mast 1.The height of the mast The maximum height of the mast is the height from the ground to the roof, minus the operating space between the top of the mast to the roof panel and the height of the sleeper. Minimum height should meet the needs of lifting height. 2.Mast position Since the mast is to be erected at the center of gravity of the travelling gantry crane between the two main girders of the trolley, the trolley must be biased, and the mast should also deviate from the centre line of the plant. The deviatio...