跳至主要内容

Operation regulation of electric chain hoist

1.A new installed or after dismantling electric hoist, should first be empty test run several times. But before the installation is completed, do not do electricity test.
2.Should be carried out in the normal use of the rated load of 125%, up from the ground about 100 mm, 10 minutes of static load test, and check the electric chain block is normal or not.
3.Dynamic load test is based on the rated load weight, for repeated movements and move around the test. After the test, check the mechanical transmission part, electrical part and the connection part is normal and reliable.
4.Not allowed to use under the environment of absolute prohibition, or exceed the rated load and rated closing times per hour (120).
5.During installation and maintenance, must strictly check the limit device is flexible and reliable, when a hook rises to an upper limit position, the distance between the hook shell to the drum shell must be greater than 50mm (10t, 16t, 20t must be greater than 120mm). When the hook to the lowest limit position, should guarantee the steel wire rope safety ring on the drum circle must be more than 2 times.
6.Not allowed pressing the switch button which in the opposite direction of the movement of the two electric hoist.
7.After the work is completed, the power supply must be pulled apart to cut off the power supply.
8.Electric hoist should be operated by professional operators who should fully grasp the safe operating procedures, slanting hanging is strictly prohibited.
9.Must be carried out by the specialized personnel on a regular basis to check the chain electric hoist, take measures in a timely manner when find failure, and carefully recorded.
10.When adjusting the glide quantity of electric hoist, should ensure that under the rated load, brake glide quantity S = V/100 (V is the stabilize rising distance in the load).

评论

此博客中的热门博文

How to deal with 3 ton electric chain hoist motor overheating

Any machine has the cycle and time of operation, is not suitable for a long time continuous operation. Long time operation will cause mechanical damage and even accidents, but in general if the 3 ton electric chain hoist surface temperature is too high, we need to check what is the reason. Firstly to check whether it is because the electric hoist weight is too large, beyond the 3 ton electric chain hoist rated weight. Overweight operation will make the motor over heating, overload for a long time will cause irreparable damage to the electric chain hoists for sale.  Electric hoist motor  is not overloaded, but still heating, should check whether the motor bearing damaged; Should also check whether the motor Work according to regulations, which is one of the reasons causing the motor heating. When the electric hoist motor is running, brake clearance is too small, not completely disengaged, causing great friction, while the frictional heating is also equivalent to the additi...

Cause analysis of the damage of electric hoist rope

Electric drum occurs  electric chain block hoist  rope breaking phenomenon after the replacement of the drum for a short time, although the rope guide device is vulnerable parts, but in addition, there is an unexplained collapse. Rope guide specifications: unless calibration, can generally be divided into for cast steel and for cast iron, the steel drum rope guide for the lifting height above 12 meters with smaller diameter, cast iron drum rope guide for lifting height below 12 meters with large diameter. After the replacement of the drum of the  electric wire rope hoist  is not the original component, it may lead to the uneven force of the guide rope, and may be because of the installation procedure or the components do not match.  WOKAITE  recommends you, if parts damaged, must try to contact the buyer at the time of the original components. The maintenance of explosion proof hoist should be carried out in accordance with GB3836.13, the danger zone r...

Overhead gantry crane lifting instructions

The overhead crane in workshop should not use mechanical lifting, because the top of the rail is close to the bottom chord of roof truss, in addition, the volume and weight of the heavy duty gantry crane are large. Small and medium sized overhead travelling gantry crane used single mast upright integral hoisting, which can improve work efficiency, shorten the construction period, reduce high-altitude operations, the construction procedures are as follows. Erecting mast 1.The height of the mast The maximum height of the mast is the height from the ground to the roof, minus the operating space between the top of the mast to the roof panel and the height of the sleeper. Minimum height should meet the needs of lifting height. 2.Mast position Since the mast is to be erected at the center of gravity of the travelling gantry crane between the two main girders of the trolley, the trolley must be biased, and the mast should also deviate from the centre line of the plant. The deviatio...