Electric chain hoist can not be avoided failure in the use, the following we have to do a summary of the motor failure. Motor burned mostly because of lack of phase or the temperature is too high. In view of these two kinds of common reason, WOKAITE technical staff has carried on the summary for the general customers safe use.
Electric chain hoist for a long time of continuous work, resulting in motor overc operation rate, and may not have good lubrication, causing the temperature is too high, so the motor will be burnt. Contactor and fuse failure, line contact error, also can cause the motor lack of phase.
The following is a common cause of motor faults and solutions:
1.Power line phase error, resulting in the role of phase protection to start, so it can not be operated.
Solution: the power line two phase on each other.
2.The power of the fuse or no fuse switch off.
Solution: check whether the current demand, the replacement for the fuse or restart no fuse switch.
3.Fuse of control circuit burn out.
Solution: check and replace the correct fuse.
4.The control circuit of the power line or wire breakage, or not good.
Solution: to repair or replace the broken and poor contact wires.
5.Power supply voltage is too low.
Solution: measure the voltage value is 10% lower than the standard supply voltage or not.
6.The motor makes a sound, but it doesn’t rotate.
Solution: check whether the motor phase is correct, repair and do a good job of insulation action.
7.Emergency switch is pressed.
Solution: to confirm the reasons for the emergency switch.
8.Poor contactor.
Solution: manual operate the hoist, if the hoist act normally, it means that the control coil or wire is poor contacted, to identify the location of bad contact and repair it; If electric chain hoist is unable to operate manually, need to check the main power supply is normal or not, if there is no title of main power supply, it must be poor contacted, unable to output normally and need to replace the contactor.
9.Contactor coil short circuit
Solution: replace the contactor
Therefore, in order to prevent the fault of motor, we must strictly follow the instructions of the operation to ensure the safety of the motor.

WOKAITE KDA030 Series crane duty motors specifications

评论

此博客中的热门博文

How to deal with 3 ton electric chain hoist motor overheating

Any machine has the cycle and time of operation, is not suitable for a long time continuous operation. Long time operation will cause mechanical damage and even accidents, but in general if the 3 ton electric chain hoist surface temperature is too high, we need to check what is the reason. Firstly to check whether it is because the electric hoist weight is too large, beyond the 3 ton electric chain hoist rated weight. Overweight operation will make the motor over heating, overload for a long time will cause irreparable damage to the electric chain hoists for sale.  Electric hoist motor  is not overloaded, but still heating, should check whether the motor bearing damaged; Should also check whether the motor Work according to regulations, which is one of the reasons causing the motor heating. When the electric hoist motor is running, brake clearance is too small, not completely disengaged, causing great friction, while the frictional heating is also equivalent to the additional load

The reason of electrical wire rope hoist does not work after starting

Mainly because of the hoist does not reach to the rated operating voltage, there are generally 3 kinds of situations: 1.Find out whether the power supply system supply power to wire rope electric hoist , generally used test pencil, such as no power supply; 2.The main control circuit of the wire rope electric hoist is damaged, the line is broken or the contact is bad, can also let the hoist motor not be electrified. This situation, need to overhaul the main control circuit. When maintenance, in order to prevent missing phase to burn the motor casused by the main control circuit supply power to three-phase motor, or hoist motor suddenly operate and cause danger, must disconnect electrical wire rope hoist motor from the power supply, only supply power to the main control circuit. Then start and stop switch, check and analyze the working condition of the electric appliance and the line, repair or replace the failed electric appliance or line. When the main control circuit is confirmed

Working level of overhead gantry crane

Overhead gantry crane  installation site and the work conditions is vary greatly, the use of lifting capacity and working frequency are also different. In order to use the crane economically and reasonably, it is necessary to choose the appropriate working level according to the working condition of the crane. The working level of the bridge crane is divided into A1 ~ A8, according to the level of the crane and the load state, that is, according to the frequency and load degree of the crane through the calculation to determine. The crane has a certain number of working cycles during its useful life. A working cycle of a  travelling gantry crane  is to start the process of loading the goods from the beginning to the next. The total number of working cycles represent the utilization of cranes. In order to facilitate the calculation, the total number of working cycles can be divided into 10 categories. 200-400 ton heavy duty travelling  overhead gantry crane for sale