1.Overloading is strictly prohibited, no unauthorized extension of the use of the handle, no use other than human power operation.
2.In lifting lifting, any work or walk under the weight are forbidden, prevent the occurrence of accidents.
3.Must confirm the parts intact before use, transmission parts and lifting chain lubrication good, normal idling.
4.Should check the upper and lower hook is hanging before use. The load on the central hook hook cavity. Lifting chain without wrong twisting and bending links, to ensure the safety.
5.When used, if you find the hand pulling force should be stopped immediately, and check:
A. Weight and other objects are implicated or not.
B. 3 ton lever hoist parts for damage or not.
C. Weight is beyond the rated load of hoist or not.
6.No illegal operation, no gourd placed in the rain or very wet places.
7.No gourd hook flipping in the middle of the chain.
8.Should do a good job in 3 ton lever chain hoist safety inspection before use, including the jaws of a manual hoist is serious wear and tear or not, wire rope should replace or not, brake surface whether there is sludge pollution problems.
9.Must be in accordance with the 3 ton lever chain hoist standard, shall not be arbitrarily extended length of the wrench, no overload, so as to avoid danger in the use of the process.
10.3 ton lever hoist should be paid attention to the timely cleaning, should be carried out the no-load test and heavy load test after maintenance, in order to ensure that the hand pull gourd in good condition should be in the ventilation, dry place properly preserved.

评论

此博客中的热门博文

How to deal with 3 ton electric chain hoist motor overheating

Any machine has the cycle and time of operation, is not suitable for a long time continuous operation. Long time operation will cause mechanical damage and even accidents, but in general if the 3 ton electric chain hoist surface temperature is too high, we need to check what is the reason. Firstly to check whether it is because the electric hoist weight is too large, beyond the 3 ton electric chain hoist rated weight. Overweight operation will make the motor over heating, overload for a long time will cause irreparable damage to the electric chain hoists for sale.  Electric hoist motor  is not overloaded, but still heating, should check whether the motor bearing damaged; Should also check whether the motor Work according to regulations, which is one of the reasons causing the motor heating. When the electric hoist motor is running, brake clearance is too small, not completely disengaged, causing great friction, while the frictional heating is also equivalent to the additi...

The reason of electrical wire rope hoist does not work after starting

Mainly because of the hoist does not reach to the rated operating voltage, there are generally 3 kinds of situations: 1.Find out whether the power supply system supply power to wire rope electric hoist , generally used test pencil, such as no power supply; 2.The main control circuit of the wire rope electric hoist is damaged, the line is broken or the contact is bad, can also let the hoist motor not be electrified. This situation, need to overhaul the main control circuit. When maintenance, in order to prevent missing phase to burn the motor casused by the main control circuit supply power to three-phase motor, or hoist motor suddenly operate and cause danger, must disconnect electrical wire rope hoist motor from the power supply, only supply power to the main control circuit. Then start and stop switch, check and analyze the working condition of the electric appliance and the line, repair or replace the failed electric appliance or line. When the main control circuit is confirmed...

Working level of overhead gantry crane

Overhead gantry crane  installation site and the work conditions is vary greatly, the use of lifting capacity and working frequency are also different. In order to use the crane economically and reasonably, it is necessary to choose the appropriate working level according to the working condition of the crane. The working level of the bridge crane is divided into A1 ~ A8, according to the level of the crane and the load state, that is, according to the frequency and load degree of the crane through the calculation to determine. The crane has a certain number of working cycles during its useful life. A working cycle of a  travelling gantry crane  is to start the process of loading the goods from the beginning to the next. The total number of working cycles represent the utilization of cranes. In order to facilitate the calculation, the total number of working cycles can be divided into 10 categories. 200-400 ton heavy duty travelling  overhead gantry crane for ...