Overhead gantry crane lifting instructions

The overhead crane in workshop should not use mechanical lifting, because the top of the rail is close to the bottom chord of roof truss, in addition, the volume and weight of the heavy duty gantry crane are large. Small and medium sized overhead travelling gantry crane used single mast upright integral hoisting, which can improve work efficiency, shorten the construction period, reduce high-altitude operations, the construction procedures are as follows.

Erecting mast

1.The height of the mast
The maximum height of the mast is the height from the ground to the roof, minus the operating space between the top of the mast to the roof panel and the height of the sleeper. Minimum height should meet the needs of lifting height.
2.Mast position
Since the mast is to be erected at the center of gravity of the travelling gantry crane between the two main girders of the trolley, the trolley must be biased, and the mast should also deviate from the centre line of the plant. The deviation should be determined according to the weight of the car, the weight of the trolley and the bias distance of the trolley.
3.The bottom treatment of the mast
The bottom of the mast should be solid and flat, laying more than two layers of sleepers, can add rail or I-beam sleepers between the two layers when necessary, laying area is determined by calculation according to the endurance, ensure the axial pressure on the ground under the mast.
4.The mast erection method
The mast can be erected by a travelling gantry crane, which is fast and safe, it can also use the crane beam to pull the mast, auxiliary mast can also be used to support mast. When the crane beam is used for erecting the mast, the stress checking of the crane beam bracket is carried out to ensure that the lateral horizontal component does not exceed 1/20 of the sum of the rated lifting capacity of the heavy duty gantry crane and the amount of the trolley.
Erect a mast, will be pre guyropes temporary mast node in the line near the mast truss, the mast was hanging to the position determined immediately, all the mooring rope fastened at the top of the mast, and tightening on the ground. For example, after the lifting of the cable or the cable stayed truss string, the temporary cable wind rope is used to pull the mast, and the fixed cable wind rope is adjusted to the proper position, then the temporary cable wind rope is loosened.
5.Hanging pulley group, set winch
For small and medium-sized travelling gantry crane, generally can be hung two sets of pulleys, lift with two winches, the distance between the location where the winch is set and the center of the mast should be greater than the length of the mast. Winch can be fixed using the plant column root, but should be block in the bundle or other protection.

Assemble carts and trolleys

Transport overhead gantry crane girder, trolley to the lifting position for assembly, after the assembly of the cart, the trolley is placed in the trolley track, and tied firmly to the cart.

Tie the cart beam

For heavy duty gantry crane below 50t, only need two sets of hanging block, generally use the cross binding method, which is: the mast lifting lugs toward the end girder of travelling gantry crane hanging lifting tackle direction, run through the top of the mast pulley rope guide pulley along the bottom of the mast to lead to hoist.
Running rope method. The utility model is characterized in that one side of the cart is crossed by a binding rope through the two card to be bundled in the opening of the beam walking table board, so that the binding rope is in the shape of “8”.
When the mast height is insufficient, the boom of the car moving pulley attached to the beam, in the top surface of the beam erecting beam, both ends of tie hanger, the sling is wound around the bottom of the beam.

Hanging test

The travelling gantry crane lift from the ground 0.3-0.5m, if without any abnormal phenomenon after 10min, then do the shaking test, reliability test of windlass, mooring rope, mast and anchor, after everything is normal, continue lifting.

Install the operating room

The heavy duty gantry crane hanging from the ground about 2.5m, build sleeper piles under the crane, and then mount the operating room on the beam. After the installation of the control room, adjust the position of the trolley, this position should be determined by calculation, so that both sides of the mast hanging point can achieve balance. Then the crane lift a small distance from the sleeper, carefully adjust the position of the trolley, to confirm the balance, and then fixed the trolley. Check other lifting facilities to ensure safe and reliability.

评论

  1. Thank you so much for taking effort to share such a useful information. Wire rope hoist

    回复删除

发表评论

此博客中的热门博文

How to deal with 3 ton electric chain hoist motor overheating

Any machine has the cycle and time of operation, is not suitable for a long time continuous operation. Long time operation will cause mechanical damage and even accidents, but in general if the 3 ton electric chain hoist surface temperature is too high, we need to check what is the reason. Firstly to check whether it is because the electric hoist weight is too large, beyond the 3 ton electric chain hoist rated weight. Overweight operation will make the motor over heating, overload for a long time will cause irreparable damage to the electric chain hoists for sale.  Electric hoist motor  is not overloaded, but still heating, should check whether the motor bearing damaged; Should also check whether the motor Work according to regulations, which is one of the reasons causing the motor heating. When the electric hoist motor is running, brake clearance is too small, not completely disengaged, causing great friction, while the frictional heating is also equivalent to the additional load

The reason of electrical wire rope hoist does not work after starting

Mainly because of the hoist does not reach to the rated operating voltage, there are generally 3 kinds of situations: 1.Find out whether the power supply system supply power to wire rope electric hoist , generally used test pencil, such as no power supply; 2.The main control circuit of the wire rope electric hoist is damaged, the line is broken or the contact is bad, can also let the hoist motor not be electrified. This situation, need to overhaul the main control circuit. When maintenance, in order to prevent missing phase to burn the motor casused by the main control circuit supply power to three-phase motor, or hoist motor suddenly operate and cause danger, must disconnect electrical wire rope hoist motor from the power supply, only supply power to the main control circuit. Then start and stop switch, check and analyze the working condition of the electric appliance and the line, repair or replace the failed electric appliance or line. When the main control circuit is confirmed

Working level of overhead gantry crane

Overhead gantry crane  installation site and the work conditions is vary greatly, the use of lifting capacity and working frequency are also different. In order to use the crane economically and reasonably, it is necessary to choose the appropriate working level according to the working condition of the crane. The working level of the bridge crane is divided into A1 ~ A8, according to the level of the crane and the load state, that is, according to the frequency and load degree of the crane through the calculation to determine. The crane has a certain number of working cycles during its useful life. A working cycle of a  travelling gantry crane  is to start the process of loading the goods from the beginning to the next. The total number of working cycles represent the utilization of cranes. In order to facilitate the calculation, the total number of working cycles can be divided into 10 categories. 200-400 ton heavy duty travelling  overhead gantry crane for sale